{"id":457946,"date":"2022-05-16T06:50:20","date_gmt":"2022-05-16T05:50:20","guid":{"rendered":"https:\/\/www.constructionnews.co.uk\/?p=457946"},"modified":"2023-07-28T12:07:56","modified_gmt":"2023-07-28T11:07:56","slug":"offsite-at-scale-inside-hs2s-prefab-factories","status":"publish","type":"post","link":"https:\/\/www.constructionnews.co.uk\/civils\/hs2\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/","title":{"rendered":"Offsite at scale: inside HS2\u2019s prefab factories"},"content":{"rendered":"<div class=\"factfile\">\n<p class=\"p1\"><strong><span class=\"s1\">Scheme<\/span>\u00a0<\/strong>Central 1 (C1) package of HS2 Phase 1 \u2013 Colne Valley Viaduct and Chiltern Tunnel, Hillingdon<\/p>\n<p class=\"p2\"><strong>Client<\/strong><span class=\"s2\">\u00a0HS2<\/span><\/p>\n<p class=\"p1\"><span class=\"s1\"><strong>Main contractor<\/strong> <\/span>Align joint venture (Bouygues Travaux Publics, Sir Robert McAlpine and VolkerFitzpatrick)<\/p>\n<p class=\"p2\"><strong>Contract value<\/strong><span class=\"s2\">\u00a0\u00a3965m<\/span><\/p>\n<p class=\"p2\"><strong>Contract awarded<\/strong><span class=\"s2\">\u00a0July 2017<\/span><\/p>\n<p class=\"p2\"><strong>Notice to proceed<\/strong><span class=\"s2\">\u00a0April 2020<\/span><\/p>\n<p class=\"p2\"><strong>Start of main works<\/strong><span class=\"s2\">\u00a0September 2020<\/span><\/p>\n<\/div>\n<p class=\"p1\"><span class=\"s1\">I<\/span>t may account for only a small sliver of the enormous HS2 megaproject, but the southern portal site to the west of London is possibly the most expansive currently working on the \u00a3107bn rail-construction scheme.<\/p>\n<p class=\"p3\"><span class=\"s1\">The task at hand is to construct the 3.4km Colne Valley Viaduct \u2013 set to become the longest railway bridge in the UK \u2013 and the 16km, twin-bore Chiltern Tunnel, the longest excavation on the HS2 route. Both of these mammoth tasks have been cut into manageable chunks through the use of prefabrication, resulting in two of the biggest offsite manufacturing projects yet tackled in the UK.<\/span><\/p>\n<p class=\"p3\">The Align joint venture \u2013 comprising Bouygues Travaux Publics, Sir Robert McAlpine and VolkerFitzpatrick \u2013 holds the \u00a3965m contract for this section of the route, the Central 1 (C1) package of HS2 Phase 1.<\/p>\n<p class=\"p3\">Align commissioned steelwork specialist Caunton Engineering to build two factories; one to prefabricate tunnel segments and the other to churn out slices of viaduct.<\/p>\n<p class=\"p3\">Both facilities are enormous. The viaduct factory stretches 100\u00a0metres in length and boasts an internal volume of 105,000 cubic metres, big enough to swallow London\u2019s Royal Albert Hall. The nearby precast factory for the Chiltern Tunnel, which is U-shaped in plan, measures 125 metres in length and has an internal volume of 110,000 cubic metres.<\/p>\n<p class=\"p3\">About 2,000 people are employed across Align\u2019s sites, the majority at Hillingdon, and they were hard at work when <i>Construction News<\/i> visited in early April. The site has the self-contained feel of a university campus, complete with halls of residence.<\/p>\n<p class=\"p3\">Workers who live beyond commuting distance have the option to stay overnight for a few days at a time in the \u2018Snooze Box\u2019, a purpose-built, onsite hotel, which was recently expanded to 160 rooms. <i>CN<\/i> did not spend the night, so can only speculate on the creature comforts on offer.<\/p>\n<h3>On a big scale<\/h3>\n<p class=\"p3\">The extent of the workforce matches the scale of the endeavour. The 3.4km viaduct is set to become the longest railway bridge in the UK, but not the straightest. Its route straddles a series of lakes and waterways in a sweeping curve, meaning that each of the 1,000 segments used in its construction has a unique shape.<\/p>\n<p class=\"p3\">Fabricating so many one-off concrete pieces, each weighing 60-140 tonnes, certainly poses a challenge, says placement site manager Seb Lewis, who is employed by Align member Bouygues Travaux Publics. \u201cThe main factors for variation between segments are the height of the segments and also the angle on the bottom slab,\u201d he says outside the factory.<\/p>\n<blockquote><p>\u201cWe place the formwork for the next segment up against the cage [of the previous one], so that the new one will [bear] against it\u201d<\/p>\n<h4>Seb Lewis, Bouygues Travaux Publics<\/h4>\n<\/blockquote>\n<p class=\"p3\">To ensure the segments fit together perfectly, the previously made segment is used in the manufacturing process of the current one. \u201cWe place the formwork for the next segment up against the cage [of the previous one], so that the new one will [bear] against it,\u201d Lewis says. \u201cIn case there are any issues with the finished face of the segment, it can then be counteracted with the next segment, as it is matched against it.\u201d<\/p>\n<p class=\"p3\">Precast segments are lined up outside the factory in their hundreds on the day of <i>CN<\/i>\u2019s visit. Align expects to begin fitting them together in the summer. A short walk away, in the tunnel\u2019s precast factory, there are variations to grapple with as the segments are produced.<\/p>\n<p class=\"p3\"><span class=\"s1\">Each of the 16,044 rings will be made up of seven different segments, meaning that about 112,000 segments will be fashioned in the factory overall. Most of the concrete segments will be reinforced with steel fibre, but about 1,200 rings will be doubly reinforced with both steel rebar and steel fibre, allowing a higher level of post-tensioning for extra rigidity. <\/span><\/p>\n<p class=\"p3\"><span class=\"s1\">\u201cThe reason why some have a ring rebar in addition to the steel fibre is because they have been designed for specific areas of the tunnel, such as cross-passages or shafts,\u201d says Align senior tunnel precast engineer Marcos Roman. Given the varying requirements, digital techniques are being used to ensure that each segment is fashioned correctly.<\/span><\/p>\n<h3>Casting process<\/h3>\n<p class=\"p3\">The casting process at the factory involves a <span class=\"s1\">10-stage carousel, with each stage taking 11\u00a0minutes. <\/span>A manager needs to press a button to indicate the work has been done to the right standard before the whole carousel can advance to the next step. The process runs continuously, 24\u00a0hours a day, five days a week, to maximise output. From the first stage of the production process each segment is fitted with a barcode, so Align can track when the work has been done on each piece and assign where each piece is due to be placed in the finished structure.<\/p>\n<p><img loading=\"lazy\" class=\"size-medium wp-image-457980 alignleft\" src=\"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-JanuaryDroneSP_DTA_7-300x169.jpg\" alt=\"\" width=\"300\" height=\"169\" srcset=\"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-JanuaryDroneSP_DTA_7-300x169.jpg 300w, https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-JanuaryDroneSP_DTA_7-230x129.jpg 230w\" sizes=\"(max-width: 300px) 100vw, 300px\" \/><\/p>\n<p class=\"p3\">\u201cIt tells you what stage the segment\u2019s production is at, when the segment has been produced, and you will be able to monitor any deterioration or need for restrengthening, which comes later, once the tunnel has been developed, by using the barcode. That removes the need for paperwork and makes the details of every single segment easily accessible,\u201d says Roman.<\/p>\n<p class=\"p3\">The same digital model and barcodes enable each piece to be tracked during fabrication and after the tunnel is complete. Once they emerge from the carousel, segments are kept inside the factory for 24 hours to avoid the risk of surface cracking due to temperature changes as the concrete cures. They are then stored outside for 14 days to gain full strength, although the supply of segments standing at the factory is currently enough for the next two to three months of tunnelling work. The intent, says Roman, is to <span class=\"s1\">avoid any possible slowdown of work once it begins.<\/span><\/p>\n<h3 class=\"p4\"><span class=\"s2\"><b>Tripling productivity<\/b><\/span><\/h3>\n<p class=\"p2\"><span class=\"s1\">As HS2 and the construction sector as a whole ramp up their work in the wake of the pandemic, they share a common byword: productivity. Efforts are continually being made to improve productivity across the precasting processes. At the viaduct factory, a transfer cart is used to support segments as they emerge, reducing the strain placed on them, says Lewis. This allows them to be moved earlier in the curing process, saving time overall.<\/span><\/p>\n<div id=\"attachment_457982\" class=\"wp-caption alignleft\" style=\"max-width: 310px;\"><img loading=\"lazy\" class=\"wp-image-457982 size-medium\" src=\"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Progress-South-Portal_CB_1-300x200.jpg\" alt=\"\" width=\"300\" height=\"200\" srcset=\"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Progress-South-Portal_CB_1-300x200.jpg 300w, https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Progress-South-Portal_CB_1-230x153.jpg 230w\" sizes=\"(max-width: 300px) 100vw, 300px\" \/><p class=\"wp-caption-text\">Segments have been designed for specific areas of the tunnel<\/p><\/div>\n<p class=\"p2\"><span class=\"s1\">\u201cBy using the transfer cart, we only have to wait for the concrete to reach 12 megapascals [in compressive strength], rather than 36 megapascals, so this triples the productivity rate when it comes to developing the segments,\u201d Lewis explains.<\/span><\/p>\n<p class=\"p3\"><span class=\"s1\">On top of that, the casting schedule has been designed so that no time is wasted waiting for the concrete to set. \u201cWe pour on a night shift at 4pm or 5pm. So, by the time the guys on the day shift come in, in the morning at 7am or 8am, that concrete has reached the required strength,\u201d he says.<\/span><\/p>\n<p class=\"p3\">At the tunnel factory, efficiency is boosted by speeding up the curing process with heat. At the final stage of production, each segment is baked at 45 degrees centigrade and 80 per cent humidity. That combination has been found to speed up the process of concrete strengthening, so curing, which would normally take 24 hours at ambient temperatures, can be accelerated to just five or six hours.<\/p>\n<p class=\"p3\">\u201cThere are multiple benefits here to the process,\u201d says Roman. \u201cYou save a lot of time finishing up each segment and you also do not have to worry about weather conditions, as the whole process is done inside the factory.\u201d<\/p>\n<h3 class=\"p4\"><span class=\"s2\"><b>Safety is \u201ca big focus\u201d<\/b><\/span><\/h3>\n<p class=\"p2\"><span class=\"s3\">Many safety risks present on the construction site can be swept away using automation. Roman says the precast tunnel factory is 95 per cent automated, which removes a host of safety issues. Removing the need for manual intervention as far as possible yields a safer and better workplace for everyone, he adds.<\/span><\/p>\n<p class=\"p3\">Roman explains that as each segment goes through 10 separate stages, conventional precast methods would require a lid to be manually placed on top of each mould at every stage.<\/p>\n<p class=\"p3\">\u201cThe problem is that these give you some ergonomic and safety issues,\u201d he says. \u201cYou need to manually lift the lids all the time, you need to clean the lids, and that might create an issue with dust, especially during cleaning activities. What we have done is we have completely removed the lids from the carousel and we have installed an automatic lid system.<\/p>\n<blockquote><p>\u201cIn the long term we are planning to have no MEWPs [mobile elevating work platforms]\u201d<\/p>\n<h4><span class=\"s1\">Marcos <\/span>Roman, <span class=\"s1\">Align<\/span><\/h4>\n<\/blockquote>\n<p class=\"p3\">\u201cThe automatic lid is designed to be of a universal shape, which will not change the shape of the segment itself but fills the same requirement. <span class=\"s3\">Just by clicking a few buttons, the carousel operator can manage everything, and wash or dismantle the lid, so we remove any ergonomic issues or any safety issues from the line.\u201d<\/span><\/p>\n<p class=\"p3\">Similarly, at the viaduct factory, minimising working from height is a \u201ckey focus\u201d, Lewis says. According to the Health and Safety Executive (HSE), falls from height are still the biggest cause of accidents in construction. \u201cIn the long term we are planning to have no MEWPs [mobile elevating work platforms],\u201d he adds.<\/p>\n<p class=\"p3\">For now, by using a dowel lifting system and a 140-tonne branch crane to lift the pre-cast segments, operatives no longer need to work at height on top of the segments themselves, minimising the danger to workers.<\/p>\n<h3 class=\"p4\"><b>Thinking of the community<\/b><\/h3>\n<p class=\"p2\">The engineering behind HS2 may be impressive and the Colne Valley Viaduct will represent an outstanding feat of construction, but it remains a bone of contention that people living in the area will not benefit directly from the rail line when it opens \u2013 no new station is planned in the vicinity.<\/p>\n<p><img loading=\"lazy\" class=\"size-medium wp-image-457977 alignleft\" src=\"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Colne-Valley-Viaduct-north-abutment-CGI-300x169.jpg\" alt=\"\" width=\"300\" height=\"169\" srcset=\"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Colne-Valley-Viaduct-north-abutment-CGI-300x169.jpg 300w, https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Colne-Valley-Viaduct-north-abutment-CGI-230x129.jpg 230w\" sizes=\"(max-width: 300px) 100vw, 300px\" \/>The use of prefabrication factories onsite has dramatically reduced the need for heavy lorries on local roads, minimising the effect on local communities. As Roman says: \u201cEverything for this project is done in-house, the idea being that it does not affect the wider communities.\u201d<\/p>\n<p class=\"p3\">The tunnel job is creating a fair amount of waste, much of it chalk, which is being dug up in the building process. This will be used on the site to create a 90ha slope, open to the public, made up of grassland and woodland. Before the job began, the site was farmland.<\/p>\n<p class=\"p3\">The idea, says Align head of communications Rob Hutchison, is that no-one will notice how much work was done onsite. \u201cWe want people to travel across the viaduct on the train and notice the beauty of the area, and not the fact that we were once at work here,\u201d he adds.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Scheme\u00a0Central 1 (C1) package of HS2 Phase 1 \u2013 Colne Valley Viaduct and Chiltern Tunnel, Hillingdon Client\u00a0HS2 Main contractor Align joint venture (Bouygues Travaux Publics, Sir Robert McAlpine and VolkerFitzpatrick) Contract value\u00a0\u00a3965m Contract awarded\u00a0July 2017 Notice to proceed\u00a0April 2020 Start of main works\u00a0September 2020 It may account for only a small sliver of the enormous &#8230;<\/p>\n","protected":false},"author":90643,"featured_media":457978,"comment_status":"open","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"ep_exclude_from_search":false},"categories":[530,549,39314,557,542],"tags":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v18.1 - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<meta name=\"description\" content=\"Scheme\u00a0Central 1 (C1) package of HS2 Phase 1 \u2013 Colne Valley Viaduct and Chiltern Tunnel, Hillingdon Client\u00a0HS2 Main contractor Align joint venture\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/\" \/>\n<meta property=\"og:locale\" content=\"en_GB\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Offsite at scale: inside HS2\u2019s prefab factories | Construction News\" \/>\n<meta property=\"og:description\" content=\"Scheme\u00a0Central 1 (C1) package of HS2 Phase 1 \u2013 Colne Valley Viaduct and Chiltern Tunnel, Hillingdon Client\u00a0HS2 Main contractor Align joint venture\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/\" \/>\n<meta property=\"og:site_name\" content=\"Construction News\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/CN.community\" \/>\n<meta property=\"article:published_time\" content=\"2022-05-16T05:50:20+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2023-07-28T11:07:56+00:00\" \/>\n<meta name=\"twitter:card\" content=\"summary\" \/>\n<meta name=\"twitter:image\" content=\"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Engineer-inspects-pre-cast-concrete-tunnel-segment-at-Chiltern-Tunnel-onsite-factory-in-Hertfordshire.jpg\" \/>\n<meta name=\"twitter:creator\" content=\"@CNplus\" \/>\n<meta name=\"twitter:site\" content=\"@CNplus\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Joshua Stein\" \/>\n\t<meta name=\"twitter:label2\" content=\"Estimated reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"9 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"WebSite\",\"@id\":\"https:\/\/www.constructionnews.co.uk\/#website\",\"url\":\"https:\/\/www.constructionnews.co.uk\/\",\"name\":\"Construction News\",\"description\":\"Read UK Construction Industry News, Analysis, Opinion and data\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/www.constructionnews.co.uk\/?s={search_term_string}\"},\"query-input\":\"required name=search_term_string\"}],\"inLanguage\":\"en-GB\"},{\"@type\":\"ImageObject\",\"@id\":\"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/#primaryimage\",\"inLanguage\":\"en-GB\",\"url\":\"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Engineer-inspects-pre-cast-concrete-tunnel-segment-at-Chiltern-Tunnel-onsite-factory-in-Hertfordshire.jpg\",\"contentUrl\":\"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Engineer-inspects-pre-cast-concrete-tunnel-segment-at-Chiltern-Tunnel-onsite-factory-in-Hertfordshire.jpg\",\"width\":1024,\"height\":683,\"caption\":\"Engineer inspects a pre-cast concrete tunnel segment at HS2\u2019s Chiltern Tunnel factory\"},{\"@type\":\"WebPage\",\"@id\":\"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/#webpage\",\"url\":\"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/\",\"name\":\"Offsite at scale: inside HS2\u2019s prefab factories | Construction News\",\"isPartOf\":{\"@id\":\"https:\/\/www.constructionnews.co.uk\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/#primaryimage\"},\"datePublished\":\"2022-05-16T05:50:20+00:00\",\"dateModified\":\"2023-07-28T11:07:56+00:00\",\"author\":{\"@id\":\"https:\/\/www.constructionnews.co.uk\/#\/schema\/person\/482eae6a8521cf09396402a7e955effc\"},\"description\":\"Scheme\u00a0Central 1 (C1) package of HS2 Phase 1 \u2013 Colne Valley Viaduct and Chiltern Tunnel, Hillingdon Client\u00a0HS2 Main contractor Align joint venture\",\"breadcrumb\":{\"@id\":\"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/#breadcrumb\"},\"inLanguage\":\"en-GB\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/\"]}]},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\/\/www.constructionnews.co.uk\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Offsite at scale: inside HS2\u2019s prefab factories\"}]},{\"@type\":\"Person\",\"@id\":\"https:\/\/www.constructionnews.co.uk\/#\/schema\/person\/482eae6a8521cf09396402a7e955effc\",\"name\":\"Joshua Stein\",\"image\":{\"@type\":\"ImageObject\",\"@id\":\"https:\/\/www.constructionnews.co.uk\/#personlogo\",\"inLanguage\":\"en-GB\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/8625f5ceef31a65fc91e25182beb7a92?s=96&d=mm&r=g\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/8625f5ceef31a65fc91e25182beb7a92?s=96&d=mm&r=g\",\"caption\":\"Joshua Stein\"},\"url\":\"https:\/\/www.constructionnews.co.uk\/author\/joshua-stein\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"description":"Scheme\u00a0Central 1 (C1) package of HS2 Phase 1 \u2013 Colne Valley Viaduct and Chiltern Tunnel, Hillingdon Client\u00a0HS2 Main contractor Align joint venture","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/","og_locale":"en_GB","og_type":"article","og_title":"Offsite at scale: inside HS2\u2019s prefab factories | Construction News","og_description":"Scheme\u00a0Central 1 (C1) package of HS2 Phase 1 \u2013 Colne Valley Viaduct and Chiltern Tunnel, Hillingdon Client\u00a0HS2 Main contractor Align joint venture","og_url":"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/","og_site_name":"Construction News","article_publisher":"https:\/\/www.facebook.com\/CN.community","article_published_time":"2022-05-16T05:50:20+00:00","article_modified_time":"2023-07-28T11:07:56+00:00","twitter_card":"summary","twitter_image":"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Engineer-inspects-pre-cast-concrete-tunnel-segment-at-Chiltern-Tunnel-onsite-factory-in-Hertfordshire.jpg","twitter_creator":"@CNplus","twitter_site":"@CNplus","twitter_misc":{"Written by":"Joshua Stein","Estimated reading time":"9 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebSite","@id":"https:\/\/www.constructionnews.co.uk\/#website","url":"https:\/\/www.constructionnews.co.uk\/","name":"Construction News","description":"Read UK Construction Industry News, Analysis, Opinion and data","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.constructionnews.co.uk\/?s={search_term_string}"},"query-input":"required name=search_term_string"}],"inLanguage":"en-GB"},{"@type":"ImageObject","@id":"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/#primaryimage","inLanguage":"en-GB","url":"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Engineer-inspects-pre-cast-concrete-tunnel-segment-at-Chiltern-Tunnel-onsite-factory-in-Hertfordshire.jpg","contentUrl":"https:\/\/cdn.ca.emap.com\/wp-content\/uploads\/sites\/8\/2022\/05\/HS2-Engineer-inspects-pre-cast-concrete-tunnel-segment-at-Chiltern-Tunnel-onsite-factory-in-Hertfordshire.jpg","width":1024,"height":683,"caption":"Engineer inspects a pre-cast concrete tunnel segment at HS2\u2019s Chiltern Tunnel factory"},{"@type":"WebPage","@id":"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/#webpage","url":"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/","name":"Offsite at scale: inside HS2\u2019s prefab factories | Construction News","isPartOf":{"@id":"https:\/\/www.constructionnews.co.uk\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/#primaryimage"},"datePublished":"2022-05-16T05:50:20+00:00","dateModified":"2023-07-28T11:07:56+00:00","author":{"@id":"https:\/\/www.constructionnews.co.uk\/#\/schema\/person\/482eae6a8521cf09396402a7e955effc"},"description":"Scheme\u00a0Central 1 (C1) package of HS2 Phase 1 \u2013 Colne Valley Viaduct and Chiltern Tunnel, Hillingdon Client\u00a0HS2 Main contractor Align joint venture","breadcrumb":{"@id":"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/#breadcrumb"},"inLanguage":"en-GB","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/"]}]},{"@type":"BreadcrumbList","@id":"https:\/\/www.constructionnews.co.uk\/contractors\/bouygues\/offsite-at-scale-inside-hs2s-prefab-factories-16-05-2022\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.constructionnews.co.uk\/"},{"@type":"ListItem","position":2,"name":"Offsite at scale: inside HS2\u2019s prefab factories"}]},{"@type":"Person","@id":"https:\/\/www.constructionnews.co.uk\/#\/schema\/person\/482eae6a8521cf09396402a7e955effc","name":"Joshua Stein","image":{"@type":"ImageObject","@id":"https:\/\/www.constructionnews.co.uk\/#personlogo","inLanguage":"en-GB","url":"https:\/\/secure.gravatar.com\/avatar\/8625f5ceef31a65fc91e25182beb7a92?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/8625f5ceef31a65fc91e25182beb7a92?s=96&d=mm&r=g","caption":"Joshua Stein"},"url":"https:\/\/www.constructionnews.co.uk\/author\/joshua-stein\/"}]}},"_links":{"self":[{"href":"https:\/\/www.constructionnews.co.uk\/wp-json\/wp\/v2\/posts\/457946"}],"collection":[{"href":"https:\/\/www.constructionnews.co.uk\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.constructionnews.co.uk\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.constructionnews.co.uk\/wp-json\/wp\/v2\/users\/90643"}],"replies":[{"embeddable":true,"href":"https:\/\/www.constructionnews.co.uk\/wp-json\/wp\/v2\/comments?post=457946"}],"version-history":[{"count":9,"href":"https:\/\/www.constructionnews.co.uk\/wp-json\/wp\/v2\/posts\/457946\/revisions"}],"predecessor-version":[{"id":458270,"href":"https:\/\/www.constructionnews.co.uk\/wp-json\/wp\/v2\/posts\/457946\/revisions\/458270"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.constructionnews.co.uk\/wp-json\/wp\/v2\/media\/457978"}],"wp:attachment":[{"href":"https:\/\/www.constructionnews.co.uk\/wp-json\/wp\/v2\/media?parent=457946"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.constructionnews.co.uk\/wp-json\/wp\/v2\/categories?post=457946"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.constructionnews.co.uk\/wp-json\/wp\/v2\/tags?post=457946"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}